3 • Operation and Maintenance
Doc. 065207-02 9/08 45
3.2.6 Completing the Run
1. Verify that a collection vessel and a waste bottle are installed (see
Section 3.1.6
and Section 3.1.7); the needle switch is down; and the
cell, collection vessel, and waste bottle doors are closed.
2. Press
START to begin the run. A typical run takes 15 to 25 minutes.
3. Monitor the run on the
STATUS screen (see Figure 3-14).
4. When the run is complete, three beeps are emitted, the
START LED
turns off, and the
STATUS screen displays IDLE.
5. Toggle the needle switch to the
UP position and remove the collection
vessel containing the extract from the holder. Refer to Section 3.3
for
post-run procedures.
6. Put on the thermal gloves (P/N 060372) provided in the ASE 150
Ship Kit (P/N 066399).
7. Remove the cell from the cell holder and place it on the cell rack
(P/N 059927) to cool.
8. Close the cell door until the next run, to save energy and prevent
anyone from accidentally touching a hot surface.
Do not attempt to open the cell door while a run is in progress.
N'ouvrez pas la porte pendant une extraction.
Halten Sie die Tür während der Extraktion geschlossen.
Cells are extremely hot after a run. Be especially cautious with cells
that have been heated over 50 °C (122 °F).
Les cellules sont extrêmement chaudes après une extraction. Faites
particulièrement attention aux cellules qui ont été chauffées à plus de
50 °C.