28 Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14
UPSs in a parallel configuration require a dedicated branch circuit that meets the following requirements:
Three-phase, 4-wire plus ground, 208Y/120V nominal (BladeUPS 12 model) or 400Y/230V nominal, 380–
415 Vac acceptable (BladeUPS 12i model)
50/60 Hz
Wall-mounted breaker that is readily accessible to the operator
Flexible or rigid metal conduit
Circuit with overcurrent protection, depending on parallel configuration (see Table 2 )
Table 2. BladeUPS Overcurrent Protection
Number of UPSs in Preassembled System
BladeUPS 12 Model BladeUPS 12i Model
1
50A 30A
2 100A 63A
3
150A 75A
4
200A 100A
5
225A 125A
6 (N+1 System)
225A 160A
NOTE For ease of wiring access with bottom entry, place the rack containing the UPSs on a
raised floor.
33..99 PPrreeppaarriinngg tthhee RRaacckk
Preparing the Rack
To prepare the rack for wiring:
1. Remove the accessory box that is located in the rear of the system behind the rack doors.
2. Verify that the following items are in the accessory box:
UPS documentation and software tools:
Software Suite CD and this user’s guide
BladeUPS: Documents, Firmware, and Installation Video CD
(2) Door Keys
CAN Bridge Card accessories:
(1) CAN Bridge Card Cable
(1) Redundant Signal Cable
Optional X-Slot card accessories
The preassembled system can be ordered with any of the optional X-Slot cards installed. Accessories
for installed cards are in the accessory box. Table 3 lists the cards and the associated accessories.