Eaton BladeUPS - Single Parallel Ready UPS Installation

Eaton BladeUPS
160 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
84 Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14
Figure 68. Connecting UPSs to the BladeUPS Bar (Bottom Entry Shown)
Plug Retainer
1
2
3
44..1155 SSiinnggllee PPaarraalllleell RReeaaddyy UUPPSS IInnssttaallllaattiioonn
CAUTION
Only qualified service personnel (such as a licensed electrician) shall perform the electrical installation. Risk of
electrical shock.
NOTE Do not make unauthorized changes to the UPSs; otherwise, damage may occur to your
equipment and void your warranty.
To install one UPS in a parallel-ready configuration:
1. Verify that the UPS is installed in a rail kit in a rack containing a BladeUPS Bar.
2. Switch off utility power to the distribution point where the parallel-ready UPS system will be connected.
Be absolutely sure there is no power.
3. Verify that all circuit breakers are in the OFF (O) position.
Single Parallel Ready UPS Installation