Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14 45
33..1133 EEBBMM IInnssttaallllaattiioonn
The BladeUPS EBM comes with all hardware required for installation in a standard EIA or JIS seismic rack-
mount configuration with square and round mounting holes. The rail assemblies adjust to mount in standard 19-
inch racks with front to rear rail distances from 61 to 81 cm (26 to 32 inches) deep.Figure 30 shows an example
EBM installation.
Figure 30. Example EBM Installations in Parallel Systems
Optional
Battery
Extension
Cables
33..1144 CChheecckkiinngg tthhee EEBBMM AAcccceessssoorriieess
Verify that the following items are included with the EBM:
• EBM front cover
• Mounting brackets and fasteners (if not already installed):
EBM Installation