54 Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14
Figure 41. Example EBM Installation in a Large Parallel System
33..1166 PPaarraalllleell SSyysstteemm IInniittiiaall SSttaarrttuupp
To start up a parallel system:
NOTE Verify that the total equipment ratings do not exceed the parallel system capacity to
prevent an overload alarm.
1. Verify that all circuit breakers on all UPSs are in the OFF (O) position (see Figure 24).