• Locate the top panel trim assemblies and the 12 screws that you removed previously.
• Replace the outside pairs of trim screws on the first trim assembly, and then replace the interior trim
screws.
• Repeat to install the second trim assembly.
13. Replace the two upper side panels:
• Locate the two upper side panels and the key.
• Slide the bottom lip of the first panel into the track above the bottom panel.
• Push the panel forward until it is flush with the rack frame.
• Snap the panel into the latches.
• Lock the upper side panels with the key.
• Repeat to install the second panel.
14. Five and six UPS preassembled systems only. Continue to section 3.12“Installing the UPS Internal
Batteries ” .
15. If installing optional EBM(s), continue to section 3.13 “EBM Installation” . Otherwise, go to section 3.16
“Parallel System Initial Startup Section” .
33..1111 BBoottttoomm EEnnttrryy IInnssttaallllaattiioonn
Bottom Entry Installation
Figure 19 shows input and output wiring in a bottom entry system.
Figure 19. Bottom Entry Wiring Installation
Bottom Entry Installation