Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14 39
To install the parallel system input and output wiring:
1. Verify that all battery circuit breakers on all UPSs are in the OFF (O) position (see Figure 20 ).
Figure 20. BladeUPS Module Rear Panel
Load
(RPM) Connector
Breaker
Input
Breaker
Battery
Breaker
2. Remove the five screws on the bottom entry wireway access cover and retain. Remove the cover and
retain (see Figure 21 ).
Figure 21. Removing the Wireway Access Cover (Bottom Entry Rack Shown)
3. Remove the six screws on the conduit landing plate and retain. Remove the plate and retain. See Figure 22
.
Bottom Entry Installation