Enable subprogram Options
•Immediate
• Individual dates
• Repeating date
•Interval
•Event
•External start
• Deactivation
• Fieldbus (optional)
Factory setting
Immediate
Immediate:
The subprogram is enabled immediately.
Individual dates:
Set the start and stop dates for enabling the
subprogram.
Repeating date:
Set the start condition, activity time and repetition
interval for the subprogram.
Interval:
Set the start condition, activity time and inactivity
time for the subprogram.
Event:
The subprogram is enabled by an event. Up to 3
measuring signals are linked to form
a start signal using And/Or logic.
External start:
The subprogram is enabled by a pulse at a binary
input configured accordingly.
Deactivation:
Subprogram 2 or 2+n is started as soon as
subprogram 1 is disabled.
(Only possible with multiple subprograms)
Fieldbus:
The subprogram is enabled by a signal from the
control system.
The settings (Immediate, Individual dates, Repeating date and Interval) that depend on the activation of the subprogram
are listed in the "Program type: Standard" section.
If Enable subprogram Event is selected:
Start condition Options
•No delay
• Date/Time
•Time
Factory setting
No delay
No delay:
The subprogram is started when the program is
enabled.
Date/Time:
Set the start date and start time for enabling the
subprogram.
Time:
Set the start time for enabling the subprogram.
Activation event
Number of events Options
•1
•2
•3
Factory setting
1
Specify how many measuring inputs (1-3) you want
to link to generate an activation signal.
Path: Menu/Setup/Sampling programs
Function Options Info