Manual: Transport, Installation and Start-Up: DC CompactCharger ECC 320 ©EnerCharge GmbH
ELECTRICAL INSTALLATION ECC 320
7. Electrical Installation ECC 320
This section deals with the electrical installation (AC/Ethernet) of the ECC 320.
Components are electrically live. Touching live parts will result in electric shock, burns or
death. Observe the following points before working on the electrical system:
Apply the 5 safety rules when carrying out installation work in the ECC 320.
Before carrying out installation work, completely de-energize the entire system.
Danger to life due to electric shock
DANGER
There is an increased risk of injury to persons performing work for which they are neither
qualied nor instructed.
The ECC 320 may only be installed by persons who are familiar with it, have been infor-
med about hazards, and have the necessary qualications.
Before installation, fulll all safety-related conditions.
WARNING
Danger due to faulty connection
The supply line must be installed hard-wired into the existing electrical installation and com-
ply with the nationally applicable legal regulations.
Deactivate all circuit breakers in the main supply line (400 V
AC
).
7.2 Specifications for the Electrical Installation
7.1 De-Energizing the Supply Line