Manual: Transport, Installation and Start-Up: DC CompactCharger ECC 320 ©EnerCharge GmbH
PREPARATION FOR INSTALLATION
> The installation environment must meet the following environmental specications:
• At least 0.5 kilometers (500 meters) away from salt water such as the sea.
• At least 3 kilometers away from heavy pollution sources, such as metallurgical plants, coal mines,
and thermal power plants.
• At least 2 kilometers away from medium pollution sources, such as chemical factories, rubber
factories and electroplating plants.
• At least 1 kilometer away from light pollution sources, such as food factories, tanneries, and boilers.
> Acclimatization:
• If there is a temperature difference of more than 15°C between transport and installation site, the
ECC320 should be acclimatized unopened for at least two hours. Immediate opening of the ECC320
can lead to water formation inside and cause damage when the device is switched on. Such dama-
ge may become apparent only at a later time under certain circumstances.
• Ideally, the charging station should be stored at the installation site a few hours beforehand. If this
is not possible, the ECC320 should not be stored outdoors or in a vehicle overnight at cold
temperatures (< 5°C).