Initial Installation
QUALIFIED INSTALLERS ONLY
45°
G
G
H
H
cLeaRance to combustibLes
90°
A
B
C
D
Side Wall
minimum Dimensions - coRneR instaLL
Warning: Clearances must be sufficient to allow for
maintenance and service.
G.
Wall to Edge of unit: 6” [15.2 cm]
H. Wall to Center of unit: 16” [40.6 cm]
Warning: Clearances must be sufficient to allow for
maintenance and service.
A.
Side Wall to Edge of unit: 12” [30.5 cm]
B. Side Wall to Center of unit: 22” [55.9 cm]
C. Back Wall to Edge of unit: 3” [7.6 cm]
D. Back Wall to Center of unit: 13” [33.0 cm]
E. Ceiling to unit: 16” [40.6 cm]
F. Floor (hard wood & linoleum) 0” [0 cm]
*Note: When installing on a carpeted surface, a hearth
pad must be used (not supplied) for air flow reasons.
minimum aLcove Dimensions:
Width 48” [121.9 cm]
Height 63” [160.0 cm]
Depth (Max.) 43” [109.2 cm]
A
E
Ceiling
Side Wall
Figure 43: Clearance to Combustibles
Figure 44: Clearance to Combustibles -
Ceiling
Figure 45: Clearance to Combustibles - Corner Install