4. Commissioning
4-8
Festo P .BE-MPA-EN en 1108e
4.3 Checking the valves and the valve/actuator combination
Note
Before commissioning the MPA-S valve terminal,
observe the specifications concerning the medium,
see “Installation” chapter, “Pilot control (pilot air supply)”
section.
The MPA-S valve terminal should be commissioned as
follows:
Commissioning variants
Activity
Preliminary test of the
pneumatic tubing
Test the valve-actuator
combination by means of the
manual override
Complete commissioning of the
overall system
Installing and connecting the
overall system.
Program control via
PLC/industrial PC.
Tab. 4/3: Commissioning variants
Commissioning the pneumatic components by means of the
manual override is described below.
Commissioning of the CPX terminal is described in the
corresponding description for the CPX bus node
(see the system description of your CPX terminal,
table “Descriptions of the CPX terminal”).