Section 5: Using the Model 9100: Procedure Mode 5.6-1
Final Width = 215mm
5.6 Procedure Mode — 'Verify Pass/Fail' &
'ISO9000 Pass/Fail' Procedures
5.6.1 Introduction
Sub-section 5.6 extends the Procedure mode access guide of sub-section 5.3, to describe
the use of the 'Verify Pass/Fail' Procedure and its variant 'ISO9000 Pass/Fail'. The
following topics are covered:
5.6.1.1 'ISO9000 Pass/Fail' Procedure.
5.6.2 'Verify Pass/Fail' or 'ISO9000 Pass/Fail' Procedure Selection.
5.6.2.1 Procedure Menu Screen for the Subject UUT Model.
5.6.2.2 Selection of 'Verify Pass/Fail' or 'ISO9000 Pass/Fail'.
5.6.3 General Sequence.
5.6.3.1 'OPERATOR PROMPT'.
5.6.3.2 'READ — PASS / FAIL NUMERIC'.
5.6.3.3 High Voltage Warning.
5.6.3.4 'PASS' / 'FAIL' Screen Keys.
5.6.3.5 'REPEAT PREV.' Key.
5.6.3.6 'ABORT' Key and End of Procedure.
5.6.1.1 'ISO9000 Pass/Fail' Procedure
The mechanics of using the 'ISO9000 Pass/Fail' procedure are virtually identical with
those for 'Verify Pass/Fail'. Except for initial selection of the procedure, the only
differences are in the number and range of test points to be verified. These will become
evident while using the programmed procedure cards, and need no further explanation
here.
When reading this sub-section for the 'ISO9000 Pass/Fail' procedure, merely substitute
'ISO9000 Pass/Fail' for 'Verify Pass/Fail'.