PanaFlow™ LC User’s Manual 101
Appendix B. Using the Clamping Fixtures
Figure 83: UCF Setup, Spacing
4. Position the clamping fixture along the horizontal plane of the pipe. It must not be on the top or
bottom of the pipe. Make sure the chains on both blocks are on the side of the fixture opposite from
the slide bar with the ruler.
Figure 84: UCF Setup, Side View
5. Wrap one of the chains around the pipe and fasten it on the J screw hook on the opposite side of the
block. Repeat this for the other chain.
Figure 85: UCF Setup, Top View
6. Using the screw hook on the blocks, tighten both chains until the fixture is secured snugly to the side
of the pipe.