8-20 C70 CAPACITOR BANK PROTECTION AND CONTROL SYSTEM – INSTRUCTION MANUAL
SETTINGS EXAMPLE CHAPTER 8: APPLICATION OF SETTINGS
8
Based on the manufacturer overvoltage data outlined, three overvoltage trip stages are applied using a factor of 0.9 for
the stage pickup overvoltage levels and half of the allowable time outlined.
Eq. 8-27
Eq. 8-28
The following setting values are programmed in the EnerVista UR Setup software.
8.4.8 Bank phase undervoltage settings
Bank undervoltage protection is required to take bank out-of-service when the supply bus voltage is lost. The pickup
setting is specified as 0.7 pu with a time delay of 1 second, based on maximum fault clearing time. The bank undervoltage
element is blocked during VT fuse fail conditions.
The following setting values are programmed in the EnerVista UR Setup software.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE C70 and is the answer not in the manual?

GE C70 Specifications

General IconGeneral
BrandGE
ModelC70
CategoryProtection Device
LanguageEnglish

Related product manuals