EasyManuals Logo

GE C70 User Manual

GE C70
702 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #592 background imageLoading...
Page #592 background image
9-6 C70 CAPACITOR BANK PROTECTION AND CONTROL SYSTEM – INSTRUCTION MANUAL
OVERVIEW CHAPTER 9: THEORY OF OPERATION
9
In this case, we have:
Eq. 9-18
The derivative is thus:
Eq. 9-19
Substituting equation 9-17 into equation 9-13, we have:
Eq. 9-20
Therefore:
Eq. 9-21
Substituting this value into equation 9-19, we get:
Eq. 9-22
Or alternately,
Eq. 9-23
The value can be expressed as:
Eq. 9-24
In this equation, ΔC
A
(pu) is the capacitance change as a per-unit of the leg capacitance, V
Spg
is the system phase-to-
ground voltage, and V
OP(2A)
(pu) is the operating signal resulting from the failure in the lower sub-string. Both voltages are in
per-unit of nominal bus phase-to-ground voltage, so V
Spg
can be taken as 1 when the system is normal (not faulted). Note
however that under external fault conditions sensitivity can be much different from the non-fault sensitivity.
In practice, k
A
is no less than 2.0 as the tap is no more than half way up the phase string. Comparing equation 9-16 with
equation 9-24, it can be seen that V
OP(2A)
(pu) ≥ V
OP(1A)
(pu), and thus that an element failure in the lower substring produces
a operating signal no smaller than the same failure in the upper sub-string. Thus V
OP(1A)
(pu) represents the worse case
sensitivity. A failure resulting in a 0.01 pu capacitance change in the leg capacitance results in an operating signal of at
least 0.01 pu of bus phase-to-ground voltage.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE C70 and is the answer not in the manual?

GE C70 Specifications

General IconGeneral
BrandGE
ModelC70
CategoryProtection Device
LanguageEnglish

Related product manuals