10 Operation
10.1 Daily inspections before operating
To ensure safety when handling the hoist, the custodian / person
determined by the operating company must carry out a daily check of
certain areas of the hoist / parts.
Any defects identified must be immediately reported to the supervisor and
rectified. Defects may only be rectified by trained personnel responsible for
maintenance and servicing.
Make sure that no one is on the roof of the car or inside the enclosure.
Always carry out visual inspections before function checks. Operation is
prohibited until the defects are rectified. The following points must be
inspected daily.
10.1.1 Visual inspections
Complete hoist
Damaged load-bearing elements/deformation
Travel path of the hoist clear
Loose parts or parts fallen off.
Damage to the car
Oil/grease leaks
Discolourations and soiling, corrosion, cracks
Green control light comes on.
Warning and instruction notices
All present and legible
Safety equipment
All present
Functional
No tampering
Switch boxes
Burnt/scorched areas
Discolourations
Moisture