PART 5
OPERATIONAL
TESTS
Air-cooled, Automatic
Standby Generators
Page 143
TABLE OF CONTENTS
SECTION TITLE PAGE
5.1 System Functional Tests 144
5.2 Setup Procedures 147
Section 5.1 – System Functional Tests
............................144
Introduction ........................................................ 144
Manual Transfer Switch Operation ....................... 144
Electrical Checks ................................................ 144
Generator Tests Under Load ................................ 145
Checking Automatic Operation ............................ 146
Section 5.2 – Setup Procedures ...................................... 147
Setting the Exercise Time .................................... 147