46
M_LS900 XP IQ Energy_EN_B
Connections - Installation
Power down: Machine - Water chiller
1. Machine:PuttheOn/Oswitchinthe"O"(O)position.
2. Water chiller: Set the general stop button to the "O"(Stop) position.
Switchothemachineinthefollowingsituations:
• when the operator is permanently leaving the machine
• in the event of physical damage (something is dropped on the machine, re, a liquid is spilled on the
machine, etc.)
• mechanical/electrical/electronicfaultssuggestingabreakdown
• if there is a major problem or the machine is jammed mechanically
• forced restart
• themachineisjammedontheparttobeengraved/marked
• themachineisjammedonanobjectintheworkarea
• external/internal cleaning
• llingthetank(Waterchiller)
Restarting
Ifthemachineortheoperatingprogramlocks,themachinemayneedtoberestarted.
1. Switchothemachine.
2. Wait approximately 30 s.
Thiswaitingtimemustberespected.Itpreventsanelectricsurgelikelytodamagethemachine'spowersupply.
3. Switch on the machine.