5-9
FIELD WORK INSTRUCTION
[Example]
* In Case of Start-Up in Simultaneous COOL/HEAT Operation Mode
* In Case of Start-Up in Cooling Operation Mode (and Changeover to Simultaneous COOL/HEAT
Operation Mode Afterward)
<Attention for Automatic COOL/HEAT Operation>
In the case that the indoor units are operated under an automatic cooling/heating operation by pressing the
AUTO COOL/HEAT switch, pay attention to the followings.
(1) Interference of Cooling Unit and Heating Unit
[Phenomenon]
In the case that more than 2 indoor units are closely installed and operated in the same room, each
indoor unit interferes with the next unit, resulting in inefficient operation.
[Countermeasure]
Do not use CH units individually for each indoor units in a same room.
In such a case, connect the indoor units in a same room to one CH unit and operate indoor units in the
same operation mode, if it is possible.
(2) Fan Operation When Changing Cooling/Heating Operation Mode
[Phenomenon]
In the case that room temperature rapidly increases during this automatic COOL/HEAT operation, the
operation mode is changed in order, heating operation => fan operation => cooling operation.
During this mode change, the fan operation continues for more than 10 minutes in order to avoid
unwanted influences to other indoor units.
[Countermeasure]
It is recommended that other systems be considered if very precise temperature control is required.
ON
Capacity
Cooling
Heating
ON
10 to 20min.
Capacity
Cooling
Heating
Cooling Heating