Step 6 Remove the conjoined heat sink and processor carrier.
1. Use a Phillips screwdriver to loosen the four screws (marked 2 in the label) in
the middle of the heat sink in a diagonal sequence. See (1) in Figure 8-30.
2. Use a Phillips screwdriver to loosen the two diagonal screws (marked 1 in the
label) on the heat sink. See (2) in Figure 8-30.
3. Lift the heat sink and place it upside down on the ESD desk.
4. Insert a
at-head screwdriver into the groove of the processor carrier, and
twist it to pry up one side of the carrier. See (3) in Figure 8-30.
NO TE
Insert only the tip of the at-head screwdriver. Do not apply excessive force.
5. Holding the other end of the carrier, remove the carrier and processor in the
arrow direction. See (4) and (5) in Figure 8-30.
Figure 8-30 Removing the heat sink and processor carrier
Step 7 Remove the processor.
NO TE
When removing a processor, hold the processor and its carrier to prevent the processor
from falling o.
To prevent damage to the pins and procesors, do not touch the pins of the processor
socket or the corresponding area on the processor.
Keep the processor away from the chassis to prevent thermal compound from falling
o.
1. Bend the edge of the carrier with the triangular hole to release the processor
from the carrier.
FusionServer Pro XH321 V5 Server Node
Maintenance and Service Guide 8 Parts Replacement
Issue 17 (2021-03-09) Copyright © Huawei Technologies Co., Ltd. 67