LUNA2000-200KWH-2H1 Smart String ESS
User Manual
Copyright © Huawei Technologies Co., Ltd.
Figure 3-2 Power-on process
3.4 Powering on the SACU
Prerequisites
You have completed the power-on check.
You have put on proper personal protective equipment (PPE).
Ensure that the power voltage of the SACU is within the operating voltage range, and the
three-phase input voltage is within the operating voltage range of the MBUS CCO.
Procedure
Step 1 Turn on the single-phase power switch that controls the power supply from the remote
transformer station to the SACU.
Step 2 Turn on the three-phase power switch that controls the power supply from the remote
transformer station to the SACU.
If the SACU supports the access of one MBUS route, turn on the corresponding
three-phase power switch.
If the SACU supports the access of two MBUS routes, turn on the corresponding
three-phase power switches.