Follow-up Procedure 
After using the installation kit, pack it back to the iron box and place it in a dry indoor place. 
2.8.4.3 Installing the Smart Rack Controller 
Prerequisites 
Unpack and check the rack controller delivered to the site to ensure that it is intact. 
Procedure 
Step 1  Remove the decorative cover and maintenance compartment cover from the rack controller. 
Figure 2-55 Removing covers 
 
 
Step 2  Install short-circuiting copper bars that are delivered with the product. 
Figure 2-56 Installing short-circuiting copper bars 
 
 
Step 3  Install the maintenance compartment cover and the decorative cover to the rack controller.