Step 5 Install the protective cover delivered with the product, connect a PE cable to the protective
cover on the left or right side, and bind the cable.
Figure 2-74 Connecting a PE cable
----End
2.9.5 Installing DC Power Cables
Prerequisites
The DC power cables have been pre-buried.
The OT/DT terminals have been crimped. For details, see Crimping an OT or DT
Terminal.
Procedure
Step 1 Remove the baffle plate in front of the power distribution area.
Step 2 Route the DC power cables through the cable hole at the bottom and connect the cables to the
DC circuit breaker.