LUNA2000-200KWH-2H1 Smart String ESS 
  User Manual   
4 SmartLogger Web-based Deployment 
 
Copyright © Huawei Technologies Co., Ltd. 
 
Allowed fluctuation of the target grid power for the 
grid-connection point 
Automatic SOC 
calibration 
 
EnabledAutomatic SOC calibration is enabled. If the total 
charge and discharge energy reaches the threshold or the 
calibration function has not been triggered for 30 days, the SOC 
automatic calibration is performed. During calibration, the 
cut-off SOC settings will be ineffective and the response of the 
charge/discharge power may be impacted temporarily. 
 
DisabledAutomatic SOC calibration is disabled. 
Set the Charge/Discharge time. A maximum of 14 time segments 
can be set. You can set a cycle by week by clicking the buttons 
corresponding to Mon. through Sun. in the Repeat box. The 
buttons are blue by default, indicating selected. After you click it, 
the button turns gray. 
 
6.  Connect to a Huawei network management system (NMS.) 
7.  Connect to a third-party management system. Select IEC104. 
8.  Connect to third-party devices. 
9.  The settings are complete. 
----End 
4.6 System Setup 
Prerequisites 
Start up the system when needed. 
Procedure 
Step 1  Choose Maintenance > Connect Device on the SmartLogger WebUI. 
Step 2  Click    in the upper right corner to start devices in batches.