Figure 2-66 Connecting cables
----End
2.9.3 Installing Battery Pack Cables
Step 1 Install copper bars for battery packs, and connect the battery rack general output power cable
and black start cable.
One ends of the battery rack general output power cable and black start cable are preinstalled before
delivery.
There are four types of copper bars delivered with the product: A, B, C, and D.
Copper bar D must be installed before copper bar B.
There are two types of M10 nuts for securing copper bars. Select a 15 mm or 16 mm socket based on
the site requirements.
When installing a nut, manually insert the nut into the screw plate, and then use a socket wrench to
completely secure the nut in place. This prevents the screw thread from being stuck or stripped due
to the deviation of the nut position.