Figure 2-68 Connecting 48 V cables to battery packs
Step 3 Connect cables to the COM ports on the battery packs.
Cables to COM-1 on Pack1 and COM-2 on Pack12 are reserved before delivery. After connecting
the cables to the battery packs, bind the cables inside the cabinet. Connect the other ends of the
cables after installing the rack controller.
Other COM port cables are delivered with the product.
The cable sequence is as follows: Pack1-2-3-4-5-6-7-8-9-10-11-12.
The cable between Pack5 and Pack6 is 04097837-08, the cable between Pack10 and Pack11 is
04097837-09, and the other cables are 04097837-06.