Before installing the UPS, note the following:
Do not install the UPS in a high-temperature, low-temperature, or damp place
that is beyond the technical
specications.
Install the UPS far away from water sources, heat sources, and inammable
and explosive materials. Keep the UPS free from direct sunlight, dust, volatile
gases, corrosive materials, and salty air.
Do not install the UPS in environments with conductive metal scraps in the
air.
The optimal operating temperatures for valve-regulated lead-acid (VRLA)
batteries are 20–30°C. Operating temperatures higher than 30°C shorten the
battery lifespan, and operating temperatures lower than 20°C reduce the
battery backup time.
Ensure that the
oor or installation support can bear the weight of the UPS,
batteries, and battery racks.
UPS5000-H-(400 kVA-600 kVA)
User Manual (100 kVA Power Module) 6 Installation
Issue 01 (2020-11-30) Copyright © Huawei Technologies Co., Ltd. 48

Table of Contents

Other manuals for Huawei UPS5000-H Series

Related product manuals