3.9 Menu – Cascade manager
The cascade manager menu has the
followingsubmenus:
Cascade manager
Status
Operating Mode
Settings
3.9.1 Menu Cascade manager -
Status
Onselectingstatus,thefollowingsubmenus
areavailable:
Cascade manager
Summary
Boilers
Thiswill now showthe status of theplant
cascade,andeachboilerinthecascade.
3.9.2 Menu Cascade manager
Status – Summary
Summary shows the actual heat capacity
being generated and the target calculated
requirement.
Summary
Actual: 0%
Requested: 0%
3.9.3 Menu Cascade manager
Status – Boilers
Summaryshowstheactualoperatingmode
andheatcapacitybeinggeneratedbyeach
boiler,thelistcanbescrolledifrequiredto
showallboilerscongured:
Boilers
Boiler 1: Off, 0%
Boiler 2: Off, 0%
3.9.4 Cascde Manager - Operating
mode
TheCascadeboilersequencecontrolcanbe
settooneofthreecontrolmethods.Select
theeldinordertoscrollthroughthethree
options.
Hours run - The sequence changeover
isdeterminedbythe number of burner-on
hours.Thehoursrunvaluecanbeadjusted
intheSettingsmenu.
Operating mode
Hours run
Done
Fixed Order-Thesequencechangeover
orderisxed.
Operating mode
Fixed order
Done
Timed-Thesequencechangeoveris
determinedbyoperatingtimeperiod.The
periodcanbeadjustedintheSettings
menu.
Operating mode
Timed
Done
Onceselected,selectDonetoconrm.
Operating mode
Timed
Done
3.9.5 Menu Cascade manager
Settings
Thesettingsmenuwillhavecontentbased
uponconguration of aSlaveheatsource
andtheselectedCascadeOperatingmode.
HoursrunorTimed.
Alloptionsareshownbelow,butnotallmay
be present.
Settings
Boiler modulation
Sequence on delay
Hours run
Settings
Boiler modulation
Sequence on delay
Hours run
Sequence order
Settings
Sequence on delay
Hours run
Sequence order
Timed
Settings
Hours Run
Sequence order
Timed
Ext. heat source sequence
Settings
Sequence order
Timed
Ext. heat source sequence
Settings
Timed
Ext. heat source sequence
3.9.6 Menu Cascade manager
Settings – Boiler modulation
Boiler modulation controls the switching
capacity set points in the cascade. Each
boilerincascadecanbeswitchedonatthe
earliest or latest modulation capacity set
point(modulationmax.),aswellasswitched
offinthesameway(modulationmin.).
Boiler modulation
Modulation max.
Modulation min.
3.9.7 Modulation max
Thiscausestherstboilerinthesequenceto
modulateuptotheModulationmaxcapacity
settingbeforeitbringsonthesecondboiler
inthesequenceandthenmodulatesdown
tomatchthecapacityofboth.Thiscontinues
foreachboiler.
Modulation max.
80%
3.9.8 Modulation min
Thiscausesthecascadetomodulatedown
totheModulationminsettingoneachboiler
beforeswitchingoneoff.Thisthencontinues
foreachboiler.
Modulation min.
30%
3.9.9 Menu Cascade manager
Settings – Sequence on delay
This parameter sets the time delay when
bringing on boilers in sequence, this is to
allowfortheboilercascadetobettermatch
theloadduringthestartofademandcycle.
Sequence on delay
10secs
3.9.10 Menu Cascade manager
Settings – Sequence order
Theorderthattheboilersruninsequence
canbeset,thisdoesnotaffecttheleadboiler
rotation.To change the order,remove the
boilernumbersinsequencebysettingthem
toNNandthenredenetheboilernumbers
as required. By default the boiler number
followsthesequencenumber.
Sequence order
Seq. 1: Boiler 01
Seq. 2: Boiler 02