3-118 BA 348-01 * 2.0 * 34801b340.fm
3 Operation
Crane-lifting the machine
☞Handle the machine with a crane as follows:
• Install and safely lock the standard bucket –seeEquipping the machine with a
standard bucket on page 3-73
• Set the drive to neutral –seePutting the machine into operation on page 3-51
• Apply the parking brake –seeParking brake on page 3-50
• Stop the engine and remove the ignition key
• Do not allow anyone to stay in the cabin, and close the doors and the engine cover
• Fasten the machine at the 4 slinging points provided to this effect with tested lifting
gear (cables, belts, hooks, shackles) of sufficient size
• Carefully raise the machine with the crane
>
2
m
Fig. 158 : Crane handling with cabin
>
2
m