PROFIBUS−DP
Before switching on
11
Commissioning
11.2
11.2.1
L
11.2−1
EDSPM−TXXX−9.0−11/2009
11.2 PROFIBUS−DP
11.2.1 Before switching on
Prior to supply voltage connection, check
l the wiring for completeness, short circuits and earth faults
l the wiring of the fieldbus
A bus terminating resistor has to be connected to the first and the last
node.
l spatial cable separation from signalling and mains cables.
) Note!
After connecting the supply voltage, the modules of the I/O
system IP20 are initialised. During the initialisation, the modules
cannot be parameterised.
l Initialisation time: approx. 10 s

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Lenze EPM-T1 Series and is the answer not in the manual?

Lenze EPM-T1 Series Specifications

General IconGeneral
BrandLenze
ModelEPM-T1 Series
CategoryI/O Systems
LanguageEnglish

Related product manuals