Turning loads
7.3 Turning a load
Lattice extension operating instructions 3 112 441 en 7 - 5
GMK 4100/4100-L/5095
11.01.2008
• (A) – First, sling the load only to the hook
block of the lattice extension (rope of the
auxiliary hoist).
• Raise the load completely with the lattice
extension.
• (B) – Only now, attach the load to the hook
block of the main boom as well (main hoist
rope).
• (A) – Now lift the load with the hook block on
the main boom until both slinging points are
at the same height.
• (B) – Slacken the hoist rope on the lattice
extension until the load is only hanging
from the hook block on the main boom.
The load has now been completed turned.