5 System Commissioning and Functions NICE5000 User Manual
- 78 -
Chapter 5 System Commissioning and Functions
5.1 System Commissioning
CAUTION
Ensure that there is no person in the shaft or car before performing commissioning on the
elevator.
Ensure that the peripheral circuit and mechanical installation are ready before performing
commissioning.
The following gure shows the commissioning procedure of the system.
Figure 5-1 Commissioning procedure of the system
End
Start
Check the peripheral
circuit
Check the encoder
Set related parameters
of the elevator
Perform motor auto-
tuning
Perform trial
inspection running
Perform shaft auto-
tuning
Perform load cell auto-
tuning
Commission the door
machine controller
Perform trial normal-
speed running
Check the leveling
accuracy
Perform riding comfort
commissioning
Perform function
commissioning
5.1.1 Check Before Commissioning
The elevator needs to be commissioned after being installed; the correct commissioning
guarantees safe and normal running of the elevator.
Before performing electric commissioning, check whether the electrical part and mechanical
part are ready for commissioning to ensure safety.
At least two persons need to be onsite during commissioning so that the power supply can
be cut off immediately when an abnormality occurs.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Monarch NICE 5000 and is the answer not in the manual?

Monarch NICE 5000 Specifications

General IconGeneral
BrandMonarch
ModelNICE 5000
CategoryController
LanguageEnglish

Related product manuals