43
www.nec-computers.com
2. At least two persons are required to install the server. Securely hold the server
and install it in the rack.
3. Firmly fit the inner rails (on the sides of the server) into the rail assemblies that
are installed on the rack, and then slowly push the server into the rack.
Figure 16: Pushing the Server into the Rack
A: Rail assembly
B: Inner rail at server side
4. When the server is locked on its way into the rack, press the release levers
(blue) on the right and left sides of the server and slowly push it in.
5. The server locks again when the server is completely pushed into the rack.
Figure 17: Pressing the Release Levers
Caution
Do not catch your fingers in the levers or rails.
Insert both inner rails straight into the rack.
A
B