ERECTION AND DISMANTLING
46
V23C_09.13
SC4000 Pos 4
Drawing 4.42. Erection form.
Platform disassembly should be carried out in the reverse or der to the
assembly.
1.
Prepare the site for the storage of platform and mast sections.
2. Dismount the mast guard nets.
3. Dismount the mast sections and de tached wall anchors.
4. Before dismounting the last three mast sections re mem ber to dis mount
the signalling bar.
5.
On the bottom position remove the railings.
6. Remove the pendant control.
4.8. PLATFORM DISASSEMBLY
NOTE:
DO NOT OVERLOAD THE PLATFORM WITH DIS MOUNTED
MAST SECTIONS!
NOTE; WHEN USING MINICHASSIS DO NOT FORGET TO
UNLOAD AND SHORTEN THE PLATFORM (MAX. LENGTH
OF PLATFORM 4.2 M) BEFORE DISMOUNTING THE THREE
LAST WALL ANCHORS!
!
Remember to ll in the erection form
(chapter 10) after assembling and
checking the platform.
All the dismounted elements should be cleaned, protected and well prepared for
transportation.