Commissioning
5.3 Basic commissioning with IOP
Converter with control units CU250D-2
68 Operating Instructions, 04/2015, FW V4.7.3, A5E34261542B AB
17.
Set the Ramp Up time in seconds.
This is the time the Inverter/motor system will take from
being given the run command, to reaching the selected
motor speed.
18.
Set the Ramp Down time in seconds.
This is the time the Inverter/motor system will take from
being given the OFF1 command, for the motor to reach
a standstill.
19.
A summary of all the settings is display.
If the settings are correct, select Continue.
20.
The final screen gives two options:
Save settings
Cancel Wizard
If save is selected, a factory reset will be performed then
the settings are saved to the Inverter memory. The loc
a-
tion of safe data is assigned using the "Parameter sa
v-
ing mode" fu
nction in "Parameter settings" in "Menu".
The basic commissioning of your converter is finished.