EasyManua.ls Logo

SKF CMSS 60 - Radial Shaft Vibration Probes; Bearing Cap Mounting

SKF CMSS 60
48 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Section 2 – Typical eddy probe arrangement plans
2-3
Radial shaft vibration probes
Referenced such that when viewed from the driver end of
the machine train, the Y (vertical) probe is on the left side
of the vertical center, and the X (horizontal) probe is on the
right side of the vertical center regardless of the direction
of shaft rotation.
Bearing cap mounting
Figure 2-7. End view (preferred).
Notes:
1 Set sealing adapter tight in bearing housing before
pulling lead wires.
2 Probe lead wires must be secured against internal
whipping and rubbing.
3 Identify leads prior to installation. Use tag numbers
as required.
4 Probes must be mounted perpendicular to shaft.
5 Do not pull thermocouple wire and probe lead wires
into same outlet without engineering department
approval.
6 Set gap volts after assembly has been installed.
7 Set gap at -8.0 ±1/2 volt (example: 40 ±2.5 mils
[1 mm ±0.06 mm]).
8 Torque mating connectors to 145 ±5 inch-ounces
(1.02 ±0.035 N-m). Wrap connectors with teflon
tape.
9 Drill 1/4” drain hole at lowest point of box (typical).
10 Preferred arrangement for probe installation:
Viewed from the driver end of the machine train,
the Y-probe (vertical) shall be to the left of vertical
center. The X-probe (horizontal) shall be to the right
of vertical center.
Figure 2-8. End view (alternate). Figure 2-9. Side view.
Notes:
1 Set sealing adapter tight in bearing housing before
pulling lead wires.
2 Probe lead wires must be secured against internal
whipping and rubbing.
3 Identify leads prior to installation. Use tag numbers
as required.
4 Probes must be mounted perpendicular to shaft.
5 Do not pull thermocouple wire and probe lead wires
into same outlet without Engineering Department
approval.
6 Set gap volts after assembly has been installed.
7 Set gap at -8.0 ±1/2 volt (example: 40 ±2.5 mils
[1 mm ±0.06 mm]).
8 Torque mating connectors to 145 ±5 inch-ounces
(1.02 ±0.035 N-m). Wrap connectors with teflon
tape.
9 Drill 1/4” drain hole at lowest point of box (typical).
10 Preferred arrangement for probe installation:
Viewed from the driver end of the machine train,
the Y-probe (vertical) shall be to the left of vertical
center. The X-probe (horizontal) shall be to the right
of vertical center.
Shaft
7
2
Rotation
CMSS 903
Series Probe
Clamp
7
2
8
4
1
3
9

Table of Contents