1. ConnecttheMinus(-)outputconnectorofthestring’sfirstpoweroptimisertothePlus(+)output
connectorofthestring’ssecondpoweroptimiser.
2.
Connecttherestofthepoweroptimisersinthestringinthesamemanner.
Figure 9: Power optimisers connected in series
3.
Ifyouintendtomonitortheinstallation,usingtheSolarEdgemonitoringplatform,recordthe
physicallocationofeachpoweroptimiser,asdescribedinCreatingLogicalandPhysicalLayoutusing
InstallationInformationonpage55.
-Three Phase Inverter with Synergy Technology Installation MAN-01-00402-1.4
20
Step 3: Connecting Power Optimisers in Strings