Step 3: Verifying Proper Activation and
Commissioning
1. SelectInformationandverifythatthecorrectfirmwareversionsareinstalledoneachinverter.
2. SelectStatusandverifythatinverterisoperatingandproducingpower(seealsoViewingSystem
Statusonpage47).
3. Verifythatthenumberofpairedoptimisersisthesameasthenumberofphysicallyinstalledpower
optimisers.
4. VerifythatadditionalconfigurationswereproperlysetbyviewingtherelevantStatusscreens.
5. VerifythatthegreeninverterLEDissteadilylit.
YourSolarEdgepowerharvestingsystemisnowoperational.
Viewing System Status
Duringnormaloperation,theStatusscreendisplaysalltheinvertersettingsandoperationstatus.Scroll
upordowntodisplayvariousstatusparametersasdescribedinthefollowingsections.
TheLEDindicationprovidesmoreinformationaboutsystemperformance;RefertoLEDsonpage23LEDs
onpage1.
To access the Status screen:
FromtheCommissioningmenuselectStatus.ThemaininverterStatusscreenisdisplayed(seebelow).
Aredororangeicon(forexample: )mayappearatthetopleftcornerofastatuscell,indicatingan
error.Thecolorindicateserrorseverity(redistopseverity).Theerrordescriptionorinformationappears
onthescreen.Taptheerrorlineformoreinformationandtroubleshootinginstructions,andreferto
ErrorsandTroubleshootingonpage70.
Agrayclockicon( )mayappearatthetopleftcornerofastatuscell,indicatingatemporarystatus,
suchasaconnectionprocess.Whentheprocessiscomplete,theicondisappearsandaconstantstatus
messageisdisplayed.
Main Inverter Status
Status
Inverter
SN 07318000C
Power
100 kW
Voltage
277 Vac
Frequency
60.9 Hz
P_OK: 138 of 141
Optimizers Connected
Server Comm.
S_OK
(LAN)
Status
Production
Switch
OFF
Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter
-Three Phase Inverter with Synergy Technology Installation MAN-01-00402-1.4
47