Site Status
TheSitestatusscreenshowstheaccumulatedstatusofallinvertersconnectedtoamasterinverterina
chain(bus)andthemasterinverterstatus.
Forinverterswithsecondaryunits,thestatusofsecondaryunitsisdisplayedonthescreen.Ifa
secondaryunitisnotoperating,itscolumnisgrayed-out.
Status
Site
Production
1.00 MW
Limit
1.00 MW
Inverters
10/10
Inverter
SN 07318000C
Power
100 kW
Voltage
277 Vac
Frequency
60.9 Hz
P_OK: 141 0f 141
Optimizers Connected
S_OK
Server Connected
Status
Production
Switch
OFF
CosPhi
1.00
Limit
Export
Country
USA2
InverterUnits
Secondary 1
N/C
Voltage
N/A
P_OK
N/A
Temperature
N/A
Fan
N/A
Primary
SN 07318000C
Voltage
850 Vdc
P_OK
47 0f 47
Temperature
156 F
Fan
OK
Secondary 2
SN 07318000E
Voltage
850 Vdc
P_OK
47 0f 47
Temperature
156 F
Fan
OK
Switch Off. Production disabled ›
Commissioning›
l Sitestatus:
o
Production:TheACoutputpower
o
Limit:Limitationsetting(ExportorProduction)
o
Inverters:Numberofconnectedinvertersinthecluster,includingthemaster.
Chapter 5: Activating, Commissioning and Configuring the System Using the Inverter
-Three Phase Inverter with Synergy Technology Installation MAN-01-00402-1.4
49