5.2 Initial start-up
When the inverter is started up for the rst time, initial setup starts automatically. This
procedure must only be carried out once during initial start-up. You can nd information
on the operation of the graphics display in Section 6.
5.2.1 Requirements
Correctly connected DC supplies (AC connection is not required)
Sufcient solar irradiation
NOTE
Entering the country incorrectly may lead to problems regarding inverter operation
and to the withdrawal of the operating license by the respective grid operator.
You can restart initial start-up on the graphics display by pressing at any
time.
Thoroughly read the manual before starting initial start-up. Contact your grid ope-
rator or the SolarMax Service Centre if you have any doubt regarding the settings
you must select.
5.2.2 Procedure
1. Switch on the inverter as described in section 5.1.1. The “Initial setup” menu will be
displayed:
2. Select the display language from the “Language” menu.
3. If necessary, update the time and the date.
– The inverter saves the date entered as the initial start-up date.
– The “Country” menu will be displayed: