87
Operation on LCD
9.6 Parallel Status
Displaying path: Menu>Parallel Status
NOTICE!
• Once inverter enters parallel system, the Today yield will be replaced by Parallel.
In Parallel Status interface, the whole system power and individual slave inverter power
can be obtained in status display of master inverter. The number displayed in the Parallel
Status interface refers to the totoal number of online inverters, for example two inverters
in parallel in the below figure.
Power 5688 W
Today 500 kWh
Battery 80%
Normal
Power 5688W
Parallel Slave
Battery 80%
Normal
====Parallel Status====
>All 2
Slave 1
====Parallel Status====
>PV
Grid
9.7 History Data
Displaying path: Menu>History Data
After entering into the History Data interface, the status of On-grid, EPS, E_Feedin, E_
USERDEF, Error Log will be displayed on the LCD as follows:
• On-grid: A record of the output and input electric energy of inverter from grid
today and the total. (through Grid terminal)
»
Output Today: Output electric energy of inverter today.
»
Output Total: Total output electric energy since the inverter actived for the
first time.
»
Input Today: Input electric energy of inverter today.
»
Input Total: Total input electric energy since the inverter activated for the
first time.