SWE90UF-2PB Operation & Maintenance Manual
When digging a deep trench, avoid collide the boom or
arm cylinder hose with ground.
Operation on flat ground
【Important】
Do not use the bucket for flat operation excessively.
Do not pull the bucket by travelling for flat operation.
Do not use the bucket by rotation for flat operation,
especially there's a large obstacle, otherwise it may
damage the machine.
Do not pull or push the soil by the bucket while travelling.
Preventing collapse
(1) Place traveling motor to the rear of machine to work.
(2) Don’t place machine at the edge of trench or
digging area.
(3) Don’t digging the earth under the machine.
Operation tips
(1) In digging work, don’t let bucket collide with crawler.
(2) Try your best to place the excavator on horizontal
ground.
(3) Don’t operate bucket as a hammer or piling machine.
Don’t slew machine to remove blocks or to break up
wall.
【
Important
】
: In order to prevent damaging hydraulic
cylinder, don’t allow bucket cylinder to collide with ground or
bucket tamping when the bucket cylinder is fully extended
(bucket fully retracted).
Adjust the digging length and depth every time to ensure every
digging is fully loaded. In order to increase throughput, full load
should be the first important goal, and then the working rate.
Don’t try to extend arm fully and drop bucket, penetrating
ground with bucket teeth to dig up rocks. These will cause
serious damage of machine.