NBC™ Flat Belt - IOM
P/N: 1118140 Rev: 07/29/2020 Page 86 of 129
CRUZCONTROL ON SITE INSTALLATION
Pre-installed on the conveyor
The CRUZcontrol Logic Assemblies are installed on the side channel of the conveyor bed.
The air supply tubing (3/8” OD X ¼” ID) for the conveyor is plumbed along the length of the
conveyor bed, passing through each Logic Assembly.
The zone control air is plumbed (1/4” OD X .160” ID) from the Logic Assembly to the zone air
pucks or cylinders.
The photoelectric sensors are mounted for each zone, along with the reflector across the
conveyor bed. The photoelectric sensors are tested to insure proper alignment with the
reflectors, as well as proper functioning of the Logic Assemblies.
Field Installation
Bed to bed connections:
Connection of air supply tubing between conveyor beds, terminating the ends of the air supply
tubing
Connection of the Logic Assembly upstream or downstream cable from the last zone of a
conveyor bed to the first zone in the next upstream conveyor bed
System connections
Connecting the air supply to the conveyor
Connecting a power supply into the string of Logic Assemblies
Adding extension, power interrupt, or adapter cables if needed
Adding auxiliary photoelectric sensors as required for lead zone and line fullconditions
Providing a release signal to the function module at the discharge zone