Operation
7.3 Power On/Off
Power On
1. Ensure that no objects of any kind are present inside the
processing area that could limit or obstruct the freedom of
movement of the mechanics of the device.
2. Ensure that all safety devices are present and fully functional and
the side panels are closed.
3. Turn on the cooling system by clockwise turning the main switch
located at the back of the system to the right.
4. Switch on the compressed air supply.
5. Turn on the main power of the machine by clockwise turning the
main switch. The main switch is located at the right front side of
the machine.
6. Turn the key switch clockwise and hold against the spring force.
As soon the machine is started, release the switch. The switch
returns to its initial position.
Notice
Only if the cooling system was switched on
beforehand, the safety circuit gets closed and the
machine can be turned on.
7. The machine starts the referencing process approx. 25 seconds
after switching it on.
8. As soon the referencing process is correctly completed and
an acoustic signal sounds, the machine is ready for operation.
Additionally the ready-to-use state is indicated through the slow
flashing of the green status LEDs.
60 ENGLISH (Translation)