5.5.4 Dry mortarless installation with fire batt
Dry mortarless installation with fire batt into a solid wall
Fig. 28: Dry mortarless installation with fire batt into a solid wall
1 FKR-EU
2.4 Coated board system
3.1 Solid wall
4.1 Solid ceiling slab
Z Spigot construction 370 mm
Flange construction 342 mm
*
Installation near the floor analogous to
Up to EI 60 S
Dry mortarless installation with fire batt in solid wall, "flange to flange"
Fig. 29: Dry mortarless installation into a solid wall, with a fire batt, flange to flange, illustration shows side by side
installation (applies also to installation of dampers on top of each other)
1 FKR-EU
2.4 Coated board system
3.1 Solid wall
4.1 Solid ceiling slab
Z Spigot construction 370 mm
Flange construction 342 mm
s2 Spigot construction 40 – 600 mm
Flange construction 80 – 600 mm
*
Installation near the floor analogous to
Up to EI 60 S
Installation
Solid walls > Dry mortarless installation with fire batt
Fire damper FKR-EU 45