MECHANICAL INSTALLATION Liebert Trinergy™ Cube
Installation Manual - 10H52243IM60 - rev. 7 - 06/2020 Page 47
2.11. CORES assembly procedure
Material required for the technician to install the UPS:
Torque wrench setting: refer to chap. 7. on page 127
Procedure for preparing the contact surfaces of the removable conductors
The CORES can be mounted on the right or left of the boxes, depending on where the CORE
DISCONNECTORS are installed.
The same mounting procedure shown here for two ratings (para. 2.11.1 on page 48 and para. 2.11.2 on page
51) can be followed for all the Liebert Trinergy
TM
Cube Systems.

Table of Contents

Other manuals for Vertiv Liebert Trinergy Cube

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Vertiv Liebert Trinergy Cube and is the answer not in the manual?

Vertiv Liebert Trinergy Cube Specifications

General IconGeneral
BrandVertiv
ModelLiebert Trinergy Cube
CategoryUPS
LanguageEnglish

Related product manuals