Networking and conguring the EV charging box
89
Operating instructions – AC SMART
Changing the date and time
You can enter the date and time manually or synchronise them with your
computer.
► Click Cong/General.
► Enter the date and time.
or
► Click Sync time with PC to synchronise the values with the PC.
► Click Save.
Adjusting the availability of the charging function
If the charging function of the EV charging box needs to be deactivated, e. g.
for a maintenance process, you can control the availability of the charging
function using the functions Available and Unavailable .
There is also the Unavailable scheduled function. If a charging process
is active, the charging function is only deactivated once the vehicle is
disconnected from the EV charging box. To start a new charging process, the
availability of the charging function must be activated once again.
► Click Cong/General.
► Set the desired function.
► Click Save.
Setting the charging phases
Charging processes with one or three charging phases are possible, depend-
ing on the vehicle. You can switch between single phase and three phase
charging during an active charging process.
► Click Cong/General.
► Adjust the charging phases.
► Click Save.
Setting the maximum limit for charging current during initial
commissioning
You must be logged in as an Admin. Electrician only!
The Installation Current Limit is dependent on the domestic installation
andthespecicationsandprovisionsapplicableonsite.Themaximumlimit
cannotexceedthespeciedEVSE current limit.
► Click Cong/General.
► Change the value.
► Click Save.
Reducing the charging current
The value User current limit [A] describes the maximum available charging
current. This value cannot exceed the upper limit for the charging current
(Installation current limit). At least 6 A is required to be able to start a
charging process. When the setting is 0 A there is no charging at all, and any
active charging process pauses.
► Click Cong/General.
► Change the value.
► Click Save.
Prerequisite