10 Drive Start-Up Procedure
62 YASKAWA TOEPC71061737B GA800 Drive Installation & Primary Operation
A - Loosen the screws and put the wire
into the opening on the terminal
block.
B - Wire with a crimp ferrule attached,
or unsoldered wire with the core
wires lightly twisted
C - Pull back the shielding and lightly
twist the end with your fingers to
keep the ends from fraying.
D - Remove approximately 5.5 mm
(0.21 in) of the covering at the end
of the wire when you do not use
crimp ferrules.
E - Blade width of 2.5 mm (0.1 in) or
less
F - Blade thickness of 0.4 mm (0.01 in)
or less
Figure 10.8 Wiring Procedure for the Control Circuit
Note:
• Do not solder the core wire. Soldered wiring connections can become loose and cause the drive to malfunction.
• Tighten all terminal screws to the correct tightening torque. Connections that are too loose or too tight can cause incorrect
operation and damage to the drive. Incorrect connections can also cause death or serious injury from fire.
• Refer to Figure 10.9 for information to prepare terminal ends of the shielded wire.
• Prepare the wire ends of shielded twisted-pair wires as shown in Figure 10.9 to use an analog reference from an external
frequency setting potentiometer to set the frequency. Connect the shield to terminal E (G) of the drive.
A - Connect the shield to terminal E (G)
of the drive.
B - Sheath
C - Insulate with electrical tape or
shrink tubing.
Figure 10.9 Prepare the Ends of Shielded Wire
3. Put the cable through the clearance in the wiring cover.
Figure 10.10 Control Circuit Wiring
4. Install the LED status ring board, front cover, and the keypad to their initial positions.