24 About the manual
Quick installation and commissioning flowchart
Task Refer to
Identify the frame size of your drive:
R1, R2, R3, R4.
Type designation label on page 51.
Plan the installation. Select the cables, etc.
Check the ambient conditions, ratings,
required cooling air flow, input power
connection, compatibility of the motor, motor
connection, and other technical data.
Planning the cabinet installation on page 39.
Planning the electrical installation on page 55.
Technical data on page 110.
Option manual (if optional equipment is
included)
Unpack and check the drive.
Check that all necessary optional modules
and equipment are present and correct.
Only intact units may be started up.
Contents of the package on page 49.
Delivery check and drive module identification
on page 50.
If the converter was non-operational for more
than one year, reform the converter DC link
capacitors. For more information, contact your
ABB representative.
Check the installation site. Checking the installation site on page 51.
Install the drive in a cabinet. Installing the drive on page 52.
Route the cables. Routing the cables on page 64.
Check the insulation of the supply cable, the
motor and the motor cable, and the resistor
cable (if present).
Checking the insulation of the assembly on
page 75.